Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84045 REL 1: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Project Number:
Title:
Idaho Fish Screening Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
84045 REL 1
Contract Title:
1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Contract Continuation:
Previous: Next:
88219: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
  • 84045 REL 15: 1994-015-00 EXP IDAHO FISH SCREENING IMPROVEMENT
Contract Status:
Closed
Contract Description:
This contract provides management and operational support for a capital construction program dedicated to the protection all life stages of anadromous fish from water diversions, improvement of juvenile and adult fish passage at diversions, and improvement of stream flow conditions. Staff will process environmental regulatory documents, provide oversight to archaeologists and consulting engineers, engage in scoping, and negotiate with private landowners for habitat projects. All projects require compliance with State of Idaho and Federal regulations including, but not limited to, IDAPA Title 42, IDAPA Title 36, National Environmental Policy Act, Clean Water Act, Endangered Species Act, Federal Land Management Policy Act, National Historical Preservation Act, and Magnuson-Stevens Fishery Conservation and Management Act.

Additionally, this contract funds one Fishery Habitat Biologist position (personnel only) that is not directly in the Anadromous Fish Screen Program.  This position is in the Salmon Region. Funding this position will accelerate the pace of implementation and completion of high-priority fish habitat projects funded from a variety of sources. These sources may include (but are not limited to) Bonneville Power, Pacific Coast Salmon Recovery Fund, Farm Bill, National Fish Passage Program, Western Native Trout Initiative, NOAA, Landowner Incentive Program, Habitat Improvement Program, etc. The primary responsibilities will be to identify potential fish habitat improvement projects, prepare proposals for funding, review and prioritize projects and proposals, coordinate activities with other public and private entities, and implement fish habitat improvement projects.

In this performance period, staff will produce designs for three screens: Lemhi 59 (L-59 work element I) , L-44 (work element J), and Pahsimeroi-08, (P-08, work element K). Under work elements D, E, and F, staff will provide management and operational support for the current capital construction program, Contract # 89620, Contract  Title 2007-399-00 Upper Salmon Screen Tributary Passage.  The Idaho Department of Fish and Game (IDFG) Anadromous Fish Screen, Passage, and Habitat Program expects to finalize designs, fabricate, install, and maintain five new fish screens including the Lemhi River-32 (L-32), Lemhi River-58B (L-58B), Lemhi River-59 (L-59), Lemhi Big Springs Creek-02 (LBSC-02), and East Fork Salmon River-16 (SEF-16).  These are all older fish screens that will be replaced with new screens designed to meet NMFS Juvenile Fish Screen Criteria.  These projects combined will screen approximately 58 cubic feet per second (c.f.s.) in critical habitat for Chinook salmon and steelhead.  Staff also will focus on pre- and post monitoring of fish passage projects, tributary inventories, and fish salvage for multiple projects.

Project Coordination: The IDFG coordinates other funding sources with this Bonneville Power Administration (BPA) contract in order to maximize the potential for anadromous fish recovery efforts in the Salmon River and Clearwater River Basins.
Account Type(s):
Expense
Contract Start Date:
08/01/2022
Contract End Date:
06/30/2023
Current Contract Value:
$393,605
Expenditures:
$393,605

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. Routine Administration of Contract 06/30/2023 06/30/2023
Produce environmental compliance documents and permits. B: 165. Complete Environmental Compliance 06/30/2023 06/30/2023
Communicate/Coordinate in Upper Salmon Basin C: 99. Communicate and coordinate with participants in habitat projects - Salmon Region 06/30/2023 06/30/2023
Preliminary plans, projects, proposals for the Salmon River Basin D: 114. Develop preliminary plans, projects, and proposals - Salmon Region 06/30/2023 06/30/2023
Coordination Meetings E: 191. Agency Project Coordination 06/30/2023 06/30/2023
Ongoing coordination for the six projects named above F: 191. Conduct Meetings for Restoration Planning 06/30/2023 06/30/2023
Stream Investigation Reports G: 115. Stream Investigations & Habitat Assessments 06/30/2023 06/30/2023
Technical Review Comments H: 122. Technical Review and Recommendations for Fisheries Projects 06/30/2023 06/30/2023
Topographic Electronic Files I: 175. Topographic Surveys - Lemhi River- 59 (L-59) Fish Screen 06/30/2023 04/07/2023
Topographic Electronic Files J: 175. Topographic Surveys - Lemhi River-44 (L-44) Fish Screen 06/30/2023 06/30/2023
Topographic Electronic Files K: 175. Topographic Surveys - Pahsimeroi River-08 (P-08) Fish Screen 06/30/2023 06/30/2023
Completed Annual Report L: 132. Submit Progress Report for the period July 1, 2019 through June 30, 2022 06/30/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine Administration of Contract
B 165 Complete Environmental Compliance
C 99 Communicate and coordinate with participants in habitat projects - Salmon Region
D 114 Develop preliminary plans, projects, and proposals - Salmon Region
E 191 Agency Project Coordination
F 191 Conduct Meetings for Restoration Planning
G 115 Stream Investigations & Habitat Assessments
H 122 Technical Review and Recommendations for Fisheries Projects
I 175 Topographic Surveys - Lemhi River- 59 (L-59) Fish Screen
J 175 Topographic Surveys - Lemhi River-44 (L-44) Fish Screen
K 175 Topographic Surveys - Pahsimeroi River-08 (P-08) Fish Screen
L 132 Submit Progress Report for the period July 1, 2019 through June 30, 2022
M 185 Periodic Status Reports for BPA